157 - ATPL Question Bank in English - Under SERA.4015(b), at what delay of a controlled flight must the submitted flight plan be amended, or cancelled and replaced? This is separate from the additional requirement to notify the Network Manager of IFR delays exceeding 15 minutes.

Question 157 - Air Law - ATPL - Airline Transport Pilot Licence

30 minutes of the estimated time of departure.
30 minutes beyond the estimated off-block time
60 minutes of the estimated time of departure.
60 minutes of the estimated time off blocks.

This is 1 of over 450 exam questions on Air Law